Tuesday, January 18, 2011

Percentage of completion method, a practice problem from a CPA book

This is an old problem about the percentage-of-completion (p-o-c) method that I have seen in two different books I'm studying out of for the FAR, and it goes like this:

1. Some Co. recognizes construction revenue and expenses using the percentage-of-completion method. During 2010, a single long-term project commenced, which concluded at the end of 2011. Information on the project follows:

2010 2011
Accounts receivable from contract $100,000 $300,000
Construction expenses 105,000 192,000
Construction in progress 122,000 364,000
Partial billings on contract 100,000 420,000

Profit recognized from the long-term construction contract in 2011 should be:
a. $50,000
b. $108,000
c. $128,000
d. $228,000

The question is asking us to calculate 2011 Profit. Normally profit for a construction contract calculated under the p-o-c method would be calculated using this formula:

Profit  =    Σ CTD

Σ CTC
  (Contract price – Σ CTC) – PY Profit

Where:
Σ CTD is Total Costs To Date;
Σ CTC is Total Expected Costs To Completion;
Contract Price is the total price of the contract;
and PY Profit is the profit recognized in Prior Years.

It may seem scary, but this is the easy way to calculate profit under the p-o-c method. Unfortunately there isn't enough information to use this equation, so we have to calculate 2011 profit indirectly.

Under the p-o-c method, three things affect the Construction in Progress (CIP) account: 1) to record accumulated costs, 2) to record recognition of interim revenue and expenses, and 3) to close the CIP and Billings account at the completion of the project. In this problem we only have to worry about 2): recording recognition of interim revenues and expenses. Expenses and revenues both get debited to CIP. Here's a t-account:


CIP (similar to WIP)
2010 Expenses
105,000
2010 Profit
x0
12/31/2010 Balance
122,000
2011 Expenses
192,000
2011 Profit
x1
12/31/2011 Balance
364,000


We don't really care about x0 in this problem, but for the record, it's $17,000. It's x1 we're after, and that's $50,000 (364,000 – 192,000 – 122,000). Your answer is a.

1 comment:

  1. Very informative and nice post. I really like your posts and your style.
    CPA Exam Classes

    ReplyDelete